Project Plan - Spring 2007
From ZenWiki
Earned Value Graph - [1]
Contents |
Iteration 4
Email: somakala@cmu.edu
Week 3 (5-Feb-07 to 11-Feb-07)
- 5-Feb-07 - Architecture Meeting: Interview Status Tool
- 7-Feb-07 - Client Presentation
- 8-Feb-07 - Week 3 (Mid point status) [2]
- 9-Feb-07 - Prototype #2 demo to client
- 11-Feb-07 - SRS update based on client comments
Week 4 (12-Feb-07 to 18-Feb-07)
- 15-Feb-07 - Week 4 (Mid point status) [3]
- 15-Feb-07 - Design for experiments, reviews and incorporating comments complete
- 15-Feb-07 - Architecture Document consolidation with inputs from various experiments
Week 5 (19-Feb-07 to 25-Feb-07)
- 21-Feb-07 - Reflections to be complete for this iteration
- 23-Feb-07 - Prototype #2 delivery to client (as per SOW)
- 25-Feb-07 - Mini ATAM planned for various experiments to be conducted in Iteration 5
- 25-Feb-07 - Reflections for Iteration 4 to be updated on Wiki
- 25-Feb-07 - Software environment, (mainly support for RCP) available
- Week 5 status [4]
Iteration 5 (26-Feb-07 to 1-Apr-07)
Week 1 (26-Feb-07 to 4-Mar-07)
- MOSP Initial draft
- Identifying new experiments
- Architecture document update, review by mentors and client
- Design proposal review by mentors
- Experiments
Week 2 (5-Mar-07 to 11-Mar-07)
- Architecture review comments from client and mentors received and incorporated
- Interview status experiment complete
- New experiments started
- Defining QA plan and CM plan
- 9-Mar-07 - MOSP
Spring Break (12-Mar-07 to 18-Mar-07)
- Progress on experiments
- Updating architectural views for new experiments
Week 3 (19-Mar-07 to 25-Mar-07)
- Inputs from new experiments merged into architecture document
- Architecture review as a team
- Implementation, wherever relevant, for experiments started
- QA (or CM) plan first draft to be done by 25-Mar-06
- Support tools (initial requirements) to be identified by 25-Mar-06
- Status so far [5]
Week 4 (26-Mar-07 to 1-Apr-07)
- Update architectural documents and send to mentors for review
- QA (or CM) plan reviewed and completed
- Prototype code should be automatically built on server
- Progress on experiments
- 28-Mar-07 - Reflections to be complete for the various proposals
- 30-Mar-07 - Prototype #3 delivery (as per SOW)
- 1-Apr-07 - Reflections for Iteration 5 to be updated on Wiki for all the proposals
- Status so far [6]
Iteration 6 (2-Apr-07 to 4-May-07)
Week 1 (2-Apr-07 to 8-Apr-07)
- 4-Apr-07 - First architecture draft sent to mentors and internally for review
- 6-Apr-07 - Get review comments and update architecture document
- 6-Apr-07 - QA plan draft complete. To be sent to review to mentors and team members (will follow doc process outlined in QA plan)
- 8-Apr-07 - New experiments use case diagram and architecture diagram should be ready
- Status at the end of the week[7]
Week 2 (9-Apr-07 to 15-Apr-07)
- 9 through 13-Apr-07 - Incorporate review comments in architecture document. Consolidate experiment information as and when data arrives
- 11-Apr-07 - CM plan first draft ready. To be sent for review to mentors and team members
- 13-Apr-07 - Start work on Verification and Validation matrix (wasnt done)
- 13-Apr-07 - New experiments completed so that all inputs can be reflected in architecture doc in time for ATAM
- 13-Apr-07 - SRS draft updated with client comments and further inputs and sent to client for review (wasnt done, moved to 20th Apr)
- 13-Apr-07 - QA plan review comments to be complete (wasnt done, moved to ??)
- 13-Apr-07 - JBoss training session
Week 3 (16-Apr-07 to 22-Apr-07)
- 16-Apr-07 - Verification and Validation matrix sent to team members and mentors for review (wasnt done)
- 16-Apr-07 - ATAM with Arch expert (Felix)
- 18-Apr-07 - Arch. doc sent to client for review (after mentor review and ATAM)
- 19-Apr-07 - ATAM with Arch expert (Tony)
- 20-Apr-07 - SRS draft updated with client comments and further inputs and sent to client for review
- 20-Apr-07 - QA plan review comments to be complete
- Status at the end of the week[8]
Week 4 (23-Apr-07 to 29-Apr-07)
- 23-Apr-07 - EOSP draft
- 28-Apr-07 - Estimations complete and conduct Wideband Delphi for estimates
- 27-Apr-07 - QA plan updated and sent to mentors for review
- 27-Apr-07 - Traceability matrix between requirements and architecture will be available
- 29-Apr-07 - CM plan first draft sent to internal reviewers for review
- 29-Apr-07 - Complete 3 open experiments and close them
- 23 thru 29 Apr 07- Fill architecture doc with information
- Status at the end of the week[9]
Week 5 (30-Apr-07 to 6-May-07)
- 30-Apr-07 - SRS to be submitted to client for signature
- 4-May-07 - EOSP Dry run with Linda
- 4-May-07 - Prototype #4 delivery
- 4-May-07 - SRS
- 4-May-07 - Architecture and other supporting documents, if relevant
- 6-May-07 - Reflections to be updated on the wiki
- Status at the end of the week[10]
Week 6 (7-May-07 to 11-May-07)
- 7-May-07 - EOSP dry run with mentors
- 10-May-07 - Complete traceability matrix
- 10-May-07 - Close the 2 open experiments